Scrum Release Burndown chart: No data available

March 18th, 2011 · No Comments · Project Management with TFS, TFS Reporting

Problem

The Release Burndown (from the VS Scrum 1.0 template) stays empty and shows "No data available".

How to fix

  1. Make sure to specify Start / End Date on the corresponding Sprint work item.
  2. Wait until the warehouse is refreshed (or invoke it manually).

(Thanks thanks to Ruiz Yi for his post on MSDN Forums)